Full-Scope Logistics & Installation of Airline Flight Simulators – Egypt ⇆ USA Project
Our Project Team was assigned to manage a highly valuable and sensitive operation involving the shipment, handling, and installation of Airline Flight Simulators and their accessories between Egypt and the USA for a key client.
- The team successfully executed comprehensive pre-planning, site surveys, discharging, lifting on-site installation, coordination with all stakeholders, and full inbound & outbound logistics operations.
- The complexity of this project stemmed from the high value and extreme sensitivity of each component during devanning, lifting, maneuvering, and on-site installation. Despite these challenges, our Project Team executed the operation seamlessly, achieving zero errors and delivering the entire project precisely on schedule.
- A sincere thank you to our First Global Logistics Project Team for their outstanding professionalism, dedication, and exceptional teamwork throughout this critical operation.
Project Details
- Job Site: Cairo Airport
- Egypt Outbound POL: Alexandria Old Port ⚓
- Egypt Inbound POD: Port Said West ⚓
- USA Port: Houston 🇺🇸
- Project Volume: 16 × 20’ DV + 5 × 40’ Flat Racks (OOG)
- Total CBM: 1,010 CBM
- Lifting Equipment Deployed: 5 Forklifts , 1 JIB , 2 Cranes , Scissor Lift
- Project Duration: 2 months
Scope of work:
- Site Surveys
- Loading, Lashing & Securing
- Inland Trucking
- Road Permits
- Port Handling
- Customs Clearance
- Container Stripping & Discharging
- Lifting & Installation
- Ocean Freight